Construction Updates

 

Commencement of the Robert S. Crane Jr., Welcome Center began Monday, April 17 with the placement of construction site equipment.  The project will occur in phases with a projected completion date in September of this year.  During the phases, you will see construction and parking availability change.  Since the demolition of the west side of the playground is within the first phase, a new fence was installed on the north side of our property on Cambridge Blvd mid-April, thanks to a private donor, creating a new play space for the preschool children.  The current playground will be closed during construction.

 

Expansion Updates

The opening of The Robert S. Crane, Jr., Welcome Center at our Cambridge Boulevard address has been impacted by the additional project scope.  We are excited about its opening and the alternates, which are positive improvements to our facilities.  We will keep you informed of its progress.

Excitement continues as Corna KoKosing begins mobilization and site work this month for our new sanctuary and spaces that support the sanctuary at our Dublin Road address.

Construction fence will surround our property facing Dublin Road to enclose the construction site and the surrounding grounds to the east.  The construction site will impact our normal traffic patterns.

  • New entrance off of Dublin Road directing you along the south side of our parking lot.
  • Patio doors next to our main entrance closest to Grace Hall, will become our new entrance. A sidewalk addition will connect the handicap parking area to the patio.  A handicap operator will be available to easily gain access into the building.
  • A change to our current traffic flow to enter and exit the hallway running along Grace Hall to the east will begin with construction.

Directional signs will be posted to assist you with all of the changes.

Thank you for your patience during this exciting time in the life of our church.

I will continue to provide updates during the construction process.  Please feel free to contact me with any questions.

Pam Jameson, Director of Facilities Ministry
(614) 488-0681 ext. 232
pjameson@fcchurch.com

 

Final Phase – October Update

By Pam Jameson

The Robert S. Crane, Jr., Welcome Center continues to excite and evolve. Timelines and procedures for the alternates are being finalized and implemented based on priority and proximity.  The alternates approved by the Governing Board include new flooring throughout the first floor public areas, restroom renovations, family restroom, painting, signage, Burkhart Meeting Room and courtyard patio. During the month of October interior improvements on the main floor will impact our normal appearance and traffic flow.  The majority of the fully funded projects are expected to be completed early November.   

Your gifts are important and necessary to continue our ministry.  If you are interested in making a gift, please contact Bruce Pontious or myself.

We appreciate your continued patience and support.  Project updates will be communicated, however please feel free to contact me with any questions in the meantime.

 

Final Phase – September Update

We are approaching the home stretch of the Robert S. Crane, Jr. Welcome Center and anticipating its completion.

The final touches of the welcome center will continue throughout the month of September. The Governing Board approved the following alternates, including estimates, to the South Campus project during their July 23 meeting.

Floors throughout First Floor, Public Areas  $122,000
Painting  $ 60,000
Signage  $ 15,000
Restroom Renovations, including Family Restroom $ 50,000
Burkhart Meeting Room/With Stain Glass $ 40,000
Courtyard  $ 10,000

Behind the scenes, we continue to seek support to fully fund the alternates. Construction timelines and procedures will be altered in order to effectively and efficiently incorporate the improvements.

We look forward to the return of our full worship schedule on Sunday, September 10. As a reminder, the 8:30 am communion and worship service normally held in Burkhart Chapel, will be temporarily held in the sanctuary choir loft until the reopening of the chapel.

The joy and blessings continue for which we are so grateful. We are eager to fully experience the improvements made possible by your generous gifts and appreciate your continued patience and support.  If you are interested in making a gift, please contact Bruce Pontious. Project updates will be communicated, however please feel free to contact me with any questions in the meantime.

Pam Jameson, Director of Facilities Ministry
(614) 488-0681 ext. 232
pjameson@fcchurch.com

 

Phase Three – August Update

Construction of the Robert S. Crane, Jr. Welcome Center has come alive and visually exciting.  Enthusiasm remains high even with the changes to our normal traffic patterns entering, existing and maneuvering within the 1320 Building.

You can expect to see and hear the following changes during August.

  • Interior Framing
  • Electrical Feed/Rough In
  • New Exterior Stone Placement.
  • Slate Roof Installation
  • Window and Wall System on South and West Exterior Walls
  • After Worship Tour of the Construction Project, late August
  • The construction fence will continue to enclose the same area since July’s Burkhart closing. The parking lot continues to be available with the exception of a slight reduction weekdays when larger equipment is being used.

 

The grand opening of the Welcome Center is on target for late September. The 8:30 am Communion and Worship Service normally held in Burkhart Chapel, will be temporarily held in the Sanctuary choir loft with the start of our fall programming schedule Sunday, September 10.

This is an important time in the life of our church.  Your continued patience and support is greatly appreciated.  Please feel free to contact me with any questions.

Blessings,

Pam Jameson, Director of Facilities Ministry
(614) 488-0681 ext. 232
pjameson@fcchurch.com

 

Phase Three – July through September

Construction of the Welcome Center is progressing as planned.  Excitement continues this month as the structure begins transforming into a building. This transformation will change our regular routine of entering and exiting the 1320 Building. Steps are being made to ensure an easy transition.

You can expect to see and hear the following changes during July.

  • The new structure will be framed and wall sheathing will be installed. Roofing materials and exterior stone is projected for the end of July early August.
  • Demolition of the south wall to the 1320 Building to create an opening and framing of the new doorway is scheduled sometime after July 4.
  • Due to the amount of work required to complete the project, Burkhart Chapel entrance, Burkhart Chapel and southwest stairway will be closed until completion of the project.
  • Barriers and signs will be posted to route traffic flow to and from the building.
  • The construction fence will continue similar to the previous phase with the exception of the north side fence expanded to close off Burkhart Entrance. The parking lot will continue to be available with the exception of a slight reduction weekdays when larger equipment is being used.

 

The project is projected for completion after the start of our fall schedule which begins on Sunday, September 10. Due to the timeline and the necessary work around Burkhart Chapel, special arrangements are being made to hold the 8:30 am communion and worship service in the Sanctuary choir loft until the new Welcome Center is open.

It is an exciting time in the life of our church. This project is an important and necessary addition to allow us to fully greet and welcome our faith community.

Your continued patience and support is appreciated during the construction of our new Welcome Center.

I will continue to provide updates during the construction process. Please feel free to contact me with any questions.

Blessings,

Pam Jameson, Director of Facilities Ministry
(614) 488-0681 ext. 232
pjameson@fcchurch.com

 

 

Phase Two Continues – June

Phase Two continues through June, which visually promises to be an exciting month!
• Generally speaking, the construction fence and parking will continue during this phase, with the exception of a slight reduction weekdays when larger equipment is being used.
• Structural steel and framing exterior walls.
• Framing Roof
• Late June/Early July Connecting to Original Building

Your continued patience and support is appreciated during the construction of our new Welcome Center. I will continue to provide updates during this process. Please feel free to contact me with any questions.

Blessings,

Pam Jameson, Director of Facilities Ministry
(614) 488-0681 ext. 232
pjameson@fcchurch.com

 

 

Phase Two
May 5 – May 31

Phase Two timeline includes the month of May through the end of June.  Due to the workload and length of this phase, I will break it down by the work that is anticipated this month.

  • Construction fence and parking will remain in place during this phase with the exception to opening the sidewalk to the southeast, as well as street parking for Sunday, May 21 special worship for the Installation of Dr. R. Glen Miles.
  • Completion of storm work and drain lines.
  • Completion of curb, gutter and sidewalk work in order to relocate the drive exiting onto Cambridge Blvd further south.
  • Foundation footers and pit for elevator.
  • Structural steel and framing exterior walls.

 

Thank you for your patience during this exciting time in the life of our church.

I will continue to provide updates during the construction process.  Please feel free to contact me with any questions.

Blessings,

Pam Jameson, Director of Facilities Ministry
(614) 488-0681 ext. 232
pjameson@fcchurch.com

 

Phase One
April 17 – May 5

  • Construction hours are scheduled Monday through Friday during the day until 4:30 pm.
  • The parking lot will be impacted during construction, however the center area and the area to the east will be available.
  • Access to and from our parking lot will happen from W. First Ave through construction.
  • Handicap and van accessible parking will be relocated to the east of the parking lot next to the Annex Building.
  • Street parking on Cambridge Blvd, church side, from the drive apron south to W. First Ave will be closed during this phase only.
  • Handicap Entrance behind the 1320 Building will be available throughout construction.
  • The Annex Building and Lincoln Road Chapel will continue their normal schedules.
  • Burkhart Entrance will only be accessible from Cambridge Blvd.

 

We are requesting sub-contractors, staff and anyone able to park further to do so, allowing closer parking for our visitors, families and those that need assistance.

This is an exciting time in the life of our church and this project is a blessing for us now and for our future.  My hope is that we can reflect on that blessing during any inconveniences that lie ahead.

I will provide updates during the construction process, however please feel free to contact me now with any questions.

 

Pam Jameson, Director of Facilities Ministry